Earthquake Proof System

Example of a panel anchor installation

Example of a panel anchor installation

Status of an equipment fixing execution

Status of an equipment fixing execution

The earthquake countermeasures for equipment to prevent slide or upset of devices or equipment on the raised floor. The installation is performed by the following methods according to the installation environment and the operating conformation of the devices and equipment.

When considering the execution of your construction, please consult maintenance companies or the manufacturers of the devices and equipment.

Backgrounds of the Vibration Test

Installation method


Installation of the panel anchor


Installation of the pedestal hook


Installation of the frame anchor


Fixing of the pedestals


Example of installation


Installation of the panel anchor


Installation of the pedestal hook


Installation of the frame anchor


Fixing of the holding feet


Counter-
measure method


Fix equipment / devices to the panel, then fix the hardware to the slab via an anchor through a turnbuckle.


Fix equipment / devices to the panel, then fix the panel to a pedestals by a turnbuckle.


Penetrating the panel from the equipment / devices, fix them to an anchor through a turnbuckle of the slab immediately below the panel.


Fix to a pedestals fastened to the slab by fixed type panel material.


The temporary transfer of devices and equipment


Unnecessary (To prevent problems, the power supplies of the equipment / devices need to be turned off during the work.)


Necessary


Necessary


Unnecessary


Anchor bolt fixing to slab


Necessary


Unnecessary
(Confirmation of the fixing strength of the holding feet to the slab is necessary.)


Necessary


Unnecessary


Exposure of the fastening hardware to devices and equipment


With exposures


With exposures


Without exposures


With exposures


Interference with the under floor wiring


With a little


Few


Few


Few

Study of the bodies of devices and equipment is necessary to select an installing method.
All methods require sufficient raised floor panel strength. In addition, the applicable Floor height is H = 300 mm or more.